2925 VIRTUAL WAY

CONSTRUCTION  UPDATE

If you have any questions or concerns regarding the construction at Broadway Tech Centre, please do not hesitate to contact Property Management via ClikFIX at 1-866-254-5349.

March 24, 2008

Construction continues with the following activities underway and scheduled to occur during the month of April 2008:

  • Final commissioning of Base Building systems is in progress
  • Interior finishes are nearing completion
  • Exterior hard and soft landscaping is in progress, and the park to the west of Building #1 is expected to open in May
  • Tenant improvement construction is underway and first occupancy is now scheduled for end of April
  • Virtual Way will open to thru traffic in conjunction with first occupancy