2910 VIRTUAL WAY CONSTRUCTION UPDATE
If you have any questions or concerns regarding the construction activity at Broadway Tech Centre, please do not hesitate to contact Property Management via ClikFIX at 1-866-254-5349.
July 19, 2010 | Two Week Look Ahead
The following work is scheduled over the next two weeks:
2910 Virtual Way (Building 4) - New Construction:
- complete parkade level P2 concrete suspended slab, walls, and columns
- continue main floor concrete suspended slab
- continue main floor concrete walls and columns
- continue plumbing connections – parkade levels
- continue electrical rough-in – parkade levels
2910 Virtual Way (Building 4) - Existing:
- continue existing footing and column upgrades – parkade level P3
- continue concrete stair core and shearwalls – parkade levels P3 and P2
- continue concrete stair core – main floor level
- continue underground plumbing work
- continue underground electrical work
- continue selective demolition – parkade level P3
- start soils anchors for shearwall 25 footing upgrade
|