March 1, 2010 | Two Week Look Ahead
The following work is scheduled over the next two weeks:
2910 Virtual Way (Building 4) & 2920 Virtual Way (Building 6)
- continue excavation and shoring
- continue soil anchor drilling in warehouse and elevator core
- continue warehouse demolition
- continue warehouse slab-on-grade removal / start detail excavation in warehouse
- continue detail excavation at footings within excavation
- continue concrete at pads, strip footings, and columns and walls
- continue mechanical underground, within excavation
2930 Virtual Way (Building 5)
- continue elevator installation
- complete work inside mechanical penthouse
- continue washroom finishes
- continue Lobby finishes
- complete flashing to roof parapets
- continue painting parkade P3 Level
- continue traffic coating parkade P2 Level
2940 Virtual Way (Building 7)
- continue elevator installation
- complete washroom finishes- all levels
- complete lobby finishes
- complete mechanical and electrical finishes on warehouse. Complete dock levelers- East landing dock
- complete S.W. corner exit stairs
- complete commissioning
- complete planter walls – S.W. Corner
- complete site preparation & blacktop – S.W. Corner
- continue elevator install – S.W. Corner
- continue deficiencies – All Areas
- Start green roof
Plaza
- continue carrier centre entrance metal cladding
- continue waterproofing the NW corner around Bldg. 5
- start landscaping – drain rock and piping
|