The following work is scheduled over the next two weeks:

Building #5

  • Completion of t-bar and light fixture removal
  • Continuation of core soil anchors
  • Commencement of shoring for concrete demolition
  • Opening of north wall for demolition

Building #7

  • Continuation of shoring and underpinning for footing removals
  • Completion of bulk excavation for cores
  • Continuation of rough-in for area drains to plaza level
  • Continuation of formwork for core footing
  • Commencement of rebar for core footing
  • Demolition of columns and footings at core

July 15 , 2008

The following work is scheduled over the next two weeks:

  • Continuation of excavation for Building #7 cores
  • Continuation of shoring for footing removals, Building #7
  • Continuation of rough-in for area drains to plaza level, Building #7
  • Commencement of formwork for core footings, Building #7
  • Continuation of selective interior demolition, Building #5
  • Continuation of core soil anchors, Building #5
  • Installation of rebar inserts at shear walls and CIP slab, Building #5
  • Installation of shoring for concrete demolition, Building #5

June 1 , 2008

The following work is scheduled over the next two weeks:

  • Roof beam and perimeter column removal
  • Block wall removal, Building 7
  • Commencement of  concrete infill walls
  • Completion of core soil anchors in Building #7 and continuation in Building #5
  • Separation of roof beam at Building #8
  • Completion of the removal of warehouse equipment and telecom lines
  • Continuation of selective demolition in Building #5
  • Commencement of  roof removal for Building #5
  • Drilling and installation of rebar inserts at shear walls and CIP slab

May 1 , 2008

The following work is scheduled over the next two weeks:

  • Selective demolition and de-construction activities within the warehouse to continue
  • Foundation upgrade work, including soil anchor drilling, foundation wall drilling and dowelling
  • Removal of roof material to south warehouse
  • Shutdown of water and gas services within the construction zone
  • Relocation of warehouse gas service, security panel, fire alarm panel and air conditioning equipment

April 17, 2008

The following work is scheduled over the next two weeks:

  • Erection of perimeter site fencing to the construction zone areas off of Hebb Avenue
  • Selective demolition and de-construction activities within the warehouse to continue
  • Foundation upgrade work, including soil anchor drilling, which is not expected to be disruptive since it is taking place within the warehouse
  • Removal of roof material to south warehouse

April 3, 2008

The following work is scheduled over the next two weeks:

  • Selective demolition and de-construction activities within the warehouse interior
  • Foundation upgrade work including soil anchor drilling, which is not expected to be disruptive since it is taking place within the warehouse
  • Shutdown of warehouse mechanical and electrical services
 

March 28, 2008

We are pleased to announce that construction of Building 5 & Building 7 at Broadway Tech Centre will proceed as planned and that the project has been awarded to Dominion Construction Inc. The buildings will be three stories each with approximately 25,000 square foot floor plates. Please click here and refer to the site plan for the location of the buildings.

 

Demolition work is scheduled to begin April 1st, 2008 and the project is expected to be completed by the end of 2009.  Access to the existing parkades will not be interrupted during construction and the sports courts will remain open. Most access to the construction site will occur via Hebb Avenue, but Virtual Way will be used when necessary. During these specific instances, we will endeavor to provide as much notice to tenants as possible and flag-persons will be utilized for public safety. Virtual Way is expected to open to thru traffic in late April, to coincide with initial occupancy at Building 1 (2925 Virtual Way).

 

We confirm that Bits & Bytes CafĂ© and Broadway Tech Flex will close March 28th, and that the Tenant Conference Room will close March 31st.  The new fitness facility and conference room were originally intended to open on April 1st; however, they are now tentatively scheduled to open May 15th, due to unanticipated permit delays. We apologize for the inconvenience to our tenants.

 

The Bread Garden is expected to open for business June 1st. We have arranged for Reel Appetites Inc. to provide food services to the campus through April and May. We plan to set up their mobile kitchen in the plaza area adjacent to the sports courts. Reel Appetites has catered on movie locations since 1984 and has served such “stars” as Sean Connery, Harrison Ford, Sharon Stone and Halle Berry.

 