December 6, 2011 | Two Week Look Ahead
The following work is scheduled over the next two weeks:
- Final mechanical and electrical finishing in progress on all levels
- Mechanical equipment commissioning and testing in progress
- Fire alarm and sprinkler system testing in progress
- Elevators substantially complete
- Parkade painting substantially complete
- Drywall and T-Bar ceilings substantially complete
- Painting in progress on main and 2nd floor levels
- Washroom finishes substantially complete
- Exterior plaza waterproofing work in progress
- Exterior plaza canopy glazing in progress
- Exterior plaza pavers in progress
- Exterior soft landscaping in progress
|